This is the track progress made so far. The diagram will be updated as we replace the line. Green track shows the parts replaced and red shows the areas that need to be completed. Each sleeper on the diagram represents 10 sleepers of the actual track.

Track restoration
12 August 2024
The arrival of the many sleepers required to restore the track. The hard work starts now.
14 September 2024
Saturday sees the work begin in earnest and new sleepers being laid and track gauge and alignment made good. Just a kilometre and around 1500 sleepers to go
25 September 2024




2 October 2024
Having secured the funding we take the first delivery of ballast
22 November 2024
Woodhorn Halt is now completed
The track at the Woodhorn Halt has now been fully restored. The original track was lifted and then new ballast and sleepers installed before re-laying the original track. All went well and we now have a fully fixed and gauged track. One last job is to lift and replace sleepers and ballast under the points but this is being left for the Ashington College Track Laying course.
25 February 2025
Aacom volunteer to help with track laying






1 March 2025
Beyond Youth

5 March 2025
RBB Give some much needed help




8 April 2025
Aacom return




